Vertical Divider
CSoT Expands T4 Capacity To 48,000 Substrates/Mo.
June 29, 2020
CSoT increased the capacity of its T4 Gen 6 OLED fab from 45,000 sheets/month to 48,000 sheets/month, increasing the overall cost of the T4 project from 35b yuan to 39b yuan ($4.95b US to $$5.5b US). The initial phase of T4 construction was completed last year and the fab has been ramping toward its 30,000 sheet/month capacity, while phase 2 is expected to begin in October (10,000 sheets/month) and phase 3 is expected to begin production in May of 2021.
June 29, 2020
CSoT increased the capacity of its T4 Gen 6 OLED fab from 45,000 sheets/month to 48,000 sheets/month, increasing the overall cost of the T4 project from 35b yuan to 39b yuan ($4.95b US to $$5.5b US). The initial phase of T4 construction was completed last year and the fab has been ramping toward its 30,000 sheet/month capacity, while phase 2 is expected to begin in October (10,000 sheets/month) and phase 3 is expected to begin production in May of 2021.